Port of Redwood City Tariff No. 8
675 Seaport Boulevard, Redwood City, California 94063
Phone: (650) 306-4150 Fax: (650) 369-7636

SECTION V - SERVICE AND FACILITIES
Item No. 500 SERVICE AND FACILITIES CHARGE APPLICATION (C) Issued:  June 2, 2006 Effective: July 1, 2006


(A) When stevedoring and terminal work are done by other than the Port of Redwood City, the Service and Facilities Charge shall be assessed against the stevedore or contractor for the ship's cargo handled through the Port's facilities. (See Note 1)

(B) The Service and Facilities Charge permits the movement of stevedoring equipment and personnel onto and around the terminal areas to and from the vessel, provides for the use of restroom area, temporary office space on the terminal and parking area for personnel working the vessel and cargo and Port security. Full Service and Facilities Charges will apply once on all cargo unloaded from a land carrier and removed by a land carrier at the Port's facilities. (See Note 2).

(C) These charges are in addition to all other applicable charges in this Tariff.

Note 1: No Service and Facilities charge will be assessed against cargo in containers as defined in Item 10.

Note 2: For all cargo received inbound, whether by land or ocean carrier at the Port's tank facility at Berth 5, a single Service and Facilities charge will be assessed only at the time of the inbound movement.

Item No. 501 SERVICE AND FACILITIES CHARGE (A) Issued:  July 1, 2008 Effective: August 1, 2008


Rates are based in dollars per 1,000 kilograms, or per cubic meter, according to vessel's manifest, except as otherwise provided.

ARTICLES RATES

Cargo, dry or liquid, N.O.S.

$ 2.68
Cargo, dry or liquid, in bulk, viz.: When handled through hopper or ship unloader system $ 1.45
When handled through pipeline between vessel and shore facility $ 1.38
Scrap metal - to vessel over conveyor system

Through July 31, 2008
Effective August 1, 2008

$ 2.16
$ 2.27
Scrap metal - N.O.S. $ 2.41